Campbell road work delayed but still within budget

Wilson Ave. construction in Campbell

CAMPBELL, Ohio (WYTV) – A construction project in Campbell has drivers dodging obstacles. The work was supposed to be done this month but that deadline looks like it won’t be met.

Brent Kovacs with the Ohio Department of Transportation said the project’s completion date was pushed back early on because of last-minute changes when it came to replacing culverts on Wilson Avenue.

Those decisions were made after receiving heavy rains in July and August. Crews monitored where the water was flowing and how the culvert was handling it.

Despite the changes, the project still remains on budget at $1.8 million.

“What we did was add some outlets to the culverts so that the culvert wouldn’t flood,” Kovacs said. “This gives the water more area to get out of that culvert and drain out.”

Crews are finishing the intermediate layer of asphalt this week and surfacing is expected to begin next week.

Kovacs said all the work should be done by the middle of November.

33 WYTV provides commenting to allow for constructive discussion on the stories we cover. In order to comment here, you acknowledge you have read and agreed to our Terms of Service. Commenters who violate these terms, including use of vulgar language or racial slurs, will be banned. Please be respectful of the opinions of others. If you see an inappropriate comment, please flag it for our moderators to review.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s